Quotations are easier to compare when each one states the same things. Ask each Competent Person to set out:
- Who is responsible: the named CP, and any FI who will assist.
- Elevations covered: every façade elevation, including recesses, sky-bridges and overhanging floor undersides where relevant.
- Visual inspection method: including whether accredited drone imagery will be used, and under what conditions.
- Close-range inspection approach: BCA's guidance specifies close-range inspection of at least 10% of each elevation's surface area, selected by risk and condition. A high building-wide percentage does not make up for an under-covered elevation.
- Access method: rope access, gondola, MEWP or scaffolding, with who arranges permits, anchors and resident notices.
- Testing: whether any testing is included or will be priced separately if the CP finds it necessary.
- Deliverables and programme: report, forms, photo records and target dates.
- Exclusions and assumptions: repairs, making-good, after-hours work, re-inspection.
Coverage percentages and methods remain the CP's professional judgment for your building. This list is a comparison aid, not a specification.
Sources
- BCA — Periodic Facade Inspection checked 13 Nov 2026
- BCA — Guidelines for Competent Person (PFI) checked 13 Nov 2026